A New Steel Frame Structure

The Show Must Go On

We successfully secured the project to install a new steel frame structure to 'over roof' the existing theatre facilities in Swindon which had developed a number of substantial leaks.

Working closely with the Theatre staff we managed to complete the project on time and on budget whilst fully working around all the live events which continued below us.

To ensure the theatre did not have to go “dark” for any significant period of time all materials were craned directly onto the roof from a nearby car park with internal tie rods being installed around the performances.

Value: £400,000

Form of Contract: JCT Intermediate with Contractors Design

Architect:  Swindon Borough Council

Structural Engineer: SDS Consulting

Start Date: July 2015

Completion Date: October 2015